NEW CAMPUS UPDATE

Just ran by our new campus and we’re getting so close! Here’s some of what’s going on right now.

• Lighting is going up in the Worship Center
• Audio and Visual centers, Cafe’, Guest Services and Admin Assistant stations are ready for counter tops
• Restroom #2 is complete in office area
• Offices are ready for flooring (only furnishings after that!)
• Foyer Restrooms and Foyer area are ready for final paint, then flooring and fixtures
• Stage lighting hardware installed
• Drop Ceiling ready for tiles everywhere except in Dream Team Center
• Exterior lighting installed
• Entry doors to Worship Center are being hung
• Final painting continues

And there’s more so be sure to check it out! This Saturday will be clean up day as we prepare to write down our dreams, promises, and prayers on the Worship Center floor Sunday after both services.

Exciting times!
Randy